Paving 2024

Starting in May 2024, Masons Mill Business Park will begin a significant paving project. We are working with our vendor to limit disruptions to parking and traffic flow, but some areas will be affected. We appreciate your patience while we update our facilities. You can also check this page frequently for updates.

UPDATES

April 29, 2024 - Initial letter sent to tenants

SCOPE

Four general areas are being paved. Please see this map for the specific areas. For what ares will be under construction at any given time, please see the maps below.

TIMING

Work will begin on May 6 and go through May 24 (weather permitting). See the table below for what areas will not be accessible on specific dates. This there are many factors that can change the schedule, so this is our best guess.

Please contact us with any questions.